Recent Construction Monitoring Projects
View more details of construction site monitoring projects completed by Bryce Monitoring.
We have worked on private-, public-, commercial-, industrial-, and infrastructure construction projects varying in value, duration, and engineering discipline.
You can view more details about the type of engineering project with a short project description. Also included are client names, project locations, project values, project duration, and project photos.
Our service creates a conducive project environment for stakeholder participation and involvement. With our construction monitoring expertise, we improve process implementation, project evaluation, and project performance.
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2022/12/5-Malmesbury-Roundabout-768x576.jpg)
Malmesbury N7 Roundabout
Client: De Zwartland Werf- Project Location: Malmesbury
- Project Value: R18 Million
- Project Duration: 12 Months
- Project End Date: 25 Aug 2023
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2022/12/4-Robertson-Reservoir-768x576.jpg)
Construction of 3ML Reservoir, Pipelines and Related Pump Work
Client: Langeberg Municipality- Project Location: Robertson
- Project Value: R23 million
- Project Duration: 10 Months
- Project End Date: 24 Jan 2023
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2022/12/3-Acsa-Contractor-2-768x576.jpg)
ACSA Symphony Way Housing Project: Site A (Contractor 2)
Client: City of Cape Town- Project Location: Delft
- Project Value: R67 million
- Project Duration: 16 Months
- Project End Date: 30 Jun 2023
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2022/12/2-Acsa-contractor-1-768x576.jpg)
ACSA Symphony Way Housing Project: Site A (Contractor 1)
Client: City of Cape Town- Project Location: Delft
- Project Value: R87 million
- Project Duration: 16 Months
- Project End Date: 30 Jun 2023
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2022/12/1-Bridge-on-distillery-road-768x575.jpg)
The Rehabilitation of the Bridge on Distillery Road
Client: Stellenbosch Municipality- Project Location: Stellenbosch
- Project Value: R32 million
- Project Duration: 12 Months
- Project End Date: 19 Jan 2023
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-19006-Witzands-water-treatment-works-20200319-768x576.jpg)
Water and Sanitation Engineering
Water Treatment Works (Pipeline) Return Flow
Client: City of Cape Town- Project Location: Atlantis, Melkbosstrand, Silwerstroom, Witzands
- Project Value: R36 million
- Project Duration: 10 Months
- Project End Date: May-20
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-15001-Burgan-Cape-Terminals2-768x512.jpg)
Multidisciplinary Engineering
Burgan Cape Terminals
Client: VTTI- Project Location: Cape Town Harbour
- Project Value: R560 million
- Project Duration: 18 Months
- Project End Date: Jun-17
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-16002-civil-engineering-services-for-Collage-Quarter-Estate-Kylemore-768x432.jpg)
Civil Infrastructure Engineering
Civil Engineering Services for Collage Quarter Estate Kylemore
Client: EZ Trade- Project Location: College Quarter Esates, Kylemore, Winelands
- Project Value: R2.2 million
- Project Duration: 12 Months
- Project End Date: Dec-16
![](https://demo.webeng.co/brycemonitoring/wp-content/uploads/sites/39/2021/07/Bryce-Monitoring-Logo-Projects-800-600.png)
Civil Infrastructure Engineering
Installation of Emergency Water Storage and Water Reticulation
Client: Western Cape Government: Departments of Education, Transport and Public Works- Project Location: Cape Town Metro and Winelands
- Project Value: R36.4 million
- Project Duration: 24 Months
- Project End Date: May-20
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-18004-Upgrading-of-the-Berg-River-Boulevard-North-Paarl-6-768x576.jpg)
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-18004-Upgrading-of-the-Berg-River-Boulevard-North-Paarl-6-768x576.jpg)
Road and Transport Engineering
Upgrading Of The Berg River Boulevard
Client: Drakenstein Municipality- Project Location: Paarl North
- Project Value: R111 million
- Project Duration: 23 Months
- Project End Date: Nov-18
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-20018-MAR-Borehole-injection-chamber-concrete-monitoring-200904-768x1024.jpg)
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-20018-MAR-Borehole-injection-chamber-concrete-monitoring-200904-768x1024.jpg)
Water and Sanitation Engineering
Concrete Borehole Injection Chambers
Client: City of Cape Town- Project Location: Cape Flats - various locations
- Project Value: R20 million
- Project Duration: 8 Months
- Project End Date: Mar-21
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-19007-multidiscipline-water-infrastructure-Atlantis-and-Silwerstroom-768x576.jpg)
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-19007-multidiscipline-water-infrastructure-Atlantis-and-Silwerstroom-768x576.jpg)
Water and Sanitation Engineering
Multidisciplinary Water Infrastructure
Client: City of Cape Town- Project Location: Atlantis, Silwerstroom, Witzands
- Project Value: R10.6 million
- Project Duration: 14 Months
- Project End Date: Jul-20
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-19008-Strandfontein-West-pipeline-construction-monitoring-2020-768x1024.jpg)
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-19008-Strandfontein-West-pipeline-construction-monitoring-2020-768x1024.jpg)
Water and Sanitation Engineering
Strandfontein West 350 Dia HDPE Pipeline and Chamber
Client: City of Cape Town- Project Location: Strandfontein
- Project Value: R6.3 million
- Project Duration: 3 Months
- Project End Date: Jan-20
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-19009-Concrete-borehole-chamber-768x576.jpg)
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-19009-Concrete-borehole-chamber-768x576.jpg)
Water and Sanitation Engineering
Multidisciplinary Water Infrastructure
Client: City of Cape Town- Project Location: Bishop Lavis, Hanover Park, Mitchells Plain
- Project Value: R16.6 million
- Project Duration: 5 Months
- Project End Date: Mar-20
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-19010-Integrated-Multidiscipline-Water-Infrastructure-Philippi-Conveyance-768x432.jpg)
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-19010-Integrated-Multidiscipline-Water-Infrastructure-Philippi-Conveyance-768x432.jpg)
Water and Sanitation Engineering
Integrated Multidisciplinary Water Infrastructure
Client: City of Cape Town- Project Location: Philippi
- Project Value: R11.3 million
- Project Duration: 3 Months
- Project End Date: Jan-20
![](https://demo.webeng.co/brycemonitoring/wp-content/uploads/sites/39/2021/07/Bryce-Monitoring-Logo-Projects-800-600.png)
![](https://demo.webeng.co/brycemonitoring/wp-content/uploads/sites/39/2021/07/Bryce-Monitoring-Logo-Projects-800-600.png)
![](https://demo.webeng.co/brycemonitoring/wp-content/uploads/sites/39/2021/07/Bryce-Monitoring-Logo-Projects-800-600.png)
![](https://demo.webeng.co/brycemonitoring/wp-content/uploads/sites/39/2021/07/Bryce-Monitoring-Logo-Projects-800-600.png)
Civil Infrastructure Engineering
Retrofitting of Water Meter Infrastructure and Water Efficiency Plumbing
Client: City of Cape Town- Project Location: Elsie's River, Ocean View, Plumstead
- Project Value: R29.8 million
- Project Duration: 16 Months
- Project End Date: Oct-20
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-20001-Mitchells-Plain-Multidiscipline-Water-Infrastructure-20200717-768x576.jpg)
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-20001-Mitchells-Plain-Multidiscipline-Water-Infrastructure-20200717-768x576.jpg)
Water and Sanitation Engineering
Multidisciplinary Water Infrastructure
Client: City of Cape Town- Project Location: Mitchells Plain
- Project Value: R20.8 million
- Project Duration: 12 Months
- Project End Date: Dec-20
![](https://demo.webeng.co/brycemonitoring/wp-content/uploads/sites/39/2021/07/Bryce-Monitoring-Logo-Projects-800-600.png)
![](https://demo.webeng.co/brycemonitoring/wp-content/uploads/sites/39/2021/07/Bryce-Monitoring-Logo-Projects-800-600.png)
![](https://demo.webeng.co/brycemonitoring/wp-content/uploads/sites/39/2021/07/Bryce-Monitoring-Logo-Projects-800-600.png)
![](https://demo.webeng.co/brycemonitoring/wp-content/uploads/sites/39/2021/07/Bryce-Monitoring-Logo-Projects-800-600.png)
Water and Sanitation Engineering
Water Infrastructure
Client: City of Cape Town- Project Location: Atlantis
- Project Value: R43.6 million
- Project Duration: 12 Months
- Project End Date: Jan-21
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-20016-CONCRETE-_-LINED-WASTE-POND-_-TEST-PUMP-RIG-ATLANTIS-20201104-768x576.jpg)
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-20016-CONCRETE-_-LINED-WASTE-POND-_-TEST-PUMP-RIG-ATLANTIS-20201104-768x576.jpg)
Structural Engineering
Concrete and Lined Waste Pond and Test Pump Rig
Client: City of Cape Town- Project Location: Atlantis
- Project Value: R9.5 million
- Project Duration: 12 Months
- Project End Date: Jan-21
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-20017-4ml-Pre-Fabricated-Sectional-Steel-Water-Tanks-20210407-768x576.jpg)
![](https://brycemonitoring.com/wp-content/uploads/sites/118/2021/07/Project-20017-4ml-Pre-Fabricated-Sectional-Steel-Water-Tanks-20210407-768x576.jpg)
Water and Sanitation Engineering
4Ml Pre-Fabricated Sectional Steel Water Tanks
Client: City of Cape Town- Project Location: Strandfontein
- Project Value: R12.9 million
- Project Duration: 8 Months
- Project End Date: Apr-21